VIVA North Clyde VIC - Update #1
- SwitchCo
- Oct 20, 2017
- 1 min read

The fuel system pre-burial test has been carried out successfully at VIVA North Clyde. This milestone involves a thorough inspection by Switch before the pipework is backfilled and concreted over. We do this to ensure that the fuel system pipework has been installed correctly and as per the design. The whole system is also tested under pressure for leaks by an independent contractor (in this case it was Leighton O’Brien), who then produces a report. This process went seamlessly on this site and works are cracking on. A big thanks for the Fuel Contractor (Enviropacific) and the Builder (Becon) for a good installation so far.