Toll Webb Dock and Burnie Wharf Upgrades, Vic - Update #2
- SwitchCo
- Oct 31, 2018
- 1 min read

Works are well underway at both Webb Dock and Burnie wharves, with the ramps half-closed at each site to allow piling and civil works to be completed whilst the ship operates. The carefully planned and timed construction methodology has allowed Toll to continue operating despite the significant works being undertaken within the operational terminals. Webb Dock has over 200 piles to be driven along the quayside, strengthening it in preparation for the new vessels next year, while Burnie currently has a jack up barge on site to begin constructing a number of mooring dolphins from the water.
We are excited to see how everything will take shape in the coming weeks and months!